CR 366 Widening
Location CR 366 (Chandler Road to Carlos G. Parker Boulevard Northwest)
Description

This project was requested by the City of Taylor. The project will upgrade the existing two-lane roadway to a three-lane roadway with a continuous center turn lane and shoulders from Chandler Rd to just north of Carlos G. Parker Blvd NW. The intersection with Carlos G. Parker Blvd NW will be realigned to eliminate the existing curve and upgraded to five lanes including turn lanes and shoulders.

The project received construction funding through the voter-approved 2019 Road Bond.

Status
 
Detailed design is being finalized by Garver and is expected to be complete in spring 2022, along with right-of-way acquisition and utility relocation. Construction is expected to begin in spring 2022 with completion anticipated in spring 2023. For a project fact sheet, click here.
Contact E-mail roads@wilco.org or phone 512-943-1195.
 
Project Map

20211108-CR366-BrandedMap