Location
|
North of RM 2338 to Ronald Reagan Boulevard
|
Description
|
The CR 245 project consists of the reconstruction of the existing two-lane CR 245 to an interim three-lane roadway, with a center turn lane and right turn lanes at specific locations. The three-lane interim roadway will be part of the future ultimate six-lane roadway. The CR 245 project was funded through the voter-approved 2019 Road Bond and is meant to improve mobility around Georgetown and Sun City. The engineering firm for the project is Bridgefarmer & Associates, Inc.
|
Status
|
Design was completed in summer 2022 by Bridgefarmer. Joe Bland is the contractor, and a groundbreaking is planned for Jan. 20 at 2 p.m. Construction is anticipated to be complete in spring 2024.
|
Contact
|
Email roads@wilco.org or phone 512-943-1195.
|