Southwest Taylor Improvements
Location Southwest Taylor between FM 3349 and FM 973 and FM 1660 to US 79


Description  

The Southwest Taylor Improvements include projects located near the new Samsung factory and are part of the County’s Long-Range Transportation Plan, which is intended to plan for current and future growth by maintaining a high level of safety, mobility, and quality of life for residents and communities.

CR 401 Reconstruction and Extension - This project will tie CR 401 into US 79 and expand the existing two-lane CR 401 to a four-lane roadway to provide more capacity for vehicles to safely travel in the area. The project also includes plans for installing a traffic signal at the intersection.

CR 404 and FM 973 Improvement Project - This project includes work at the intersection of FM 973 and CR 404 which will widen both roads to be three lanes; one lane in each direction with a center turn lane. The project also includes plans for installing a traffic signal at the intersection when traffic warrants.

Samsung Highway (Future County Road) - The roadway will connect FM 3349 to FM 973 and will construct a four-lane road to reduce curves on CR 404 and increase safety. The interim roadway will be completed in segments. Segment 1 will connect CR 404 to FM 973 and Segment 2 will connect FM 3349 to CR 404.



Status

CR 401 Reconstruction and Extension - James Construction has been contracted for this project. Construction began in May 2022 and is expected to finish in summer 2023.

CR 404 and FM 973 Improvement Project - HNTB is the engineer on this project. Jordan Foster is the contractor. A groundbreaking will be held on Jan. 18, 2023, at 10 a.m. at the southeast corner of CR 404 and FM 973. Construction is anticipated to be completed in summer 2023.

Samsung Highway Segment 1 between CR 404 to FM 973 - HNTB is the engineer on this project. Construction began in summer 2022 and finish in fall 2023.

Samsung Highway Segment 2 between FM 3349 to CR 404 - RPS is the engineer on this project. Construction is expected to begin in early 2023 and finish in fall 2024.

For information on the Southeast Loop, visit the project page

Contact Email roads@wilco.org or phone 512-943-1195
 