CR 129
Location CR 129 (South of Brushy Creek to North of the Southern Williamson County Line)
Description   The project will adjust roadway elevation to address sight-distance issues. Williamson County will maintain two lanes in the project area, reconstructing the existing 10-foot lanes as 11-foot lanes and adding two-foot shoulders. The project is being completed as part of the voter-approved 2019 Road Bond.
Status Preliminary design is underway by Garver. Final design is expected by summer 2021, followed by right-of-way acquisition. Construction is expected to begin in spring 2022 and be completed in fall 2022. To view a project fact sheet, click here.
Contact Email roads@wilco.org or phone 512-943-1195.
 