en-USes-MX
CR 176 at RM 2243
Location CR 176 from RM 2243 to Parkside Parkway
Description The project will realign the intersection of CR 176 with RM 2243 and reconstruct / widen the lanes of CR 176 from RM 2243 to Parkside Parkway
Status

Design was completed by WSB. The contractor is Joe Bland Construction. Environmental work was finalized by SWCA. A groundbreaking ceremony was held Friday, August 2, 2019. Construction was completed and the road was open to traffic on July 10, 2020. The safety improvement plans include adding a little over half a mile of shared use path from the Parkside neighborhood to Leander Road for shared use between pedestrians and bicycle riders. This portion of the project is expected to be completed by August, weather permitting.

Contact

E-mail roads@wilco.org or phone 512-943-3370.

 

 
Project Map
CR 176 at RM 2243