Streets to be Resurfaced Next

 The 2017 Neighborhood Street Resurfacing Program will begin in early April. Road and Bridge will notify residents of the work in advance by door hangers, flashing message signs or static message signs. When this occurs, please monitor the section below titled “Streets to be Resurfaced Next” for an updated list of streets to be resurfaced the next two days.

 PLEASE CHECK BACK FOR WEATHER DELAYS 

The following streets are scheduled to be resurfaced next:

 

 Resurfacing Date

 Neighborhood

 Street

 Treatment

Wednesday, August 9  Eastview Ranchettes  Eastview Drive
 Dove Valley Drive
   Seal Coat
Thursday, August 24  Rowe Valley  Estates  Rowe Valley Drive
    Seal Coat

   Updated  7/27/2017

  Seal Coa
  Seal Coat
  Seal Coat
  Seal Coat
 Ranch at Cypress Creek
 Ranch at Cypress Creek
       Seal Coat

     Seal Coat

 Ranch at Cypress Creek

  Seal Coat
  Seal Coat



 Live Oak Trls
 Live Oak Trls
 
On your resurfacing day

To help us provide a quality product, please do not park vehicles on the street between 9:00 am and 3:00 pm and do not run your sprinklers on your designated resurfacing day.

For seal coat, please drive slowly for a couple of weeks while the asphalt cures.

For fog seal, please and do not drive on the new surface for approximately 2-3 hours after it is applied. Temperature, humidity and cloud cover may increase curing time.   

The Williamson County Road and Bridge Department will notify residents in advance of the work by door hangers, flashing message signs, or static message signs. If your subdivision is receiving door hangers, you can expect to receive a green door hanger approximately 2 weeks in advance of the work and an orange door hanger approximately 2-3 days in advance. If your subdivision is receiving a flashing message board, the message board will be placed approximately a week in advance of the work. After receiving advance notification, please check this page to see if your street is scheduled for the next two days of work.

 
2017 Tentative Resurfacing Schedule

 

Below is the tentative 2017 Neighborhood Street Resurfacing Program Schedule. Click here to see if your street will be resurfaced in the next two days.

Neighborhood

Seal Coat

 Fog Seal

 (Cul-de-sacs only)

Vista Oaks

Early to mid-April

 Fall or early Winter

Ranch at Cypress Creek

Late April to early May

 Fall or early Winter

Deerfield Village

Mid-May

 Fall or early Winter

Heights at Deerfield

Mid-May

 Fall or early Winter

Greenfields

Mid-May

 Fall or early Winter

Wildwood Country

Mid-May

 Fall or early Winter

Old Oak Estates

Mid-May

 Fall or early Winter

Woodhollow

Mid-May

 Fall or early Winter

Red Bud Acres

Mid-May

 Fall or early Winter

West View Dr

Mid-May

 Fall or early Winter

Wild Plumb Valley

Mid to late May

 Fall or early Winter

Tri View Estates

Mid to late May

 Fall or early Winter

Jackrabbit Subdivision

Mid to late May

 Fall or early Winter

Morningside Estates

Mid to late May

 Fall or early Winter

Chandler Creek

Early June

 Fall or early Winter

Bobby Turner’s Subdivision     

Mid-June

 Fall or early Winter

Jackie Thomison

Mid-June

 Fall or early Winter

Spring Creek Ranch

Mid-June

 Fall or early Winter

Whitetail

Mid to late June

 Fall or early Winter

Durham Park

Mid to late June

 Fall or early Winter

Liberty Oaks

Mid-July

 Fall or early Winter

Cole Drive Estates

Mid-July

 Fall or early Winter

Gamefield

Mid to late July

 Fall or early Winter

Live Oak Trails

Mid to late July

 Fall or early Winter

Hilltop Estates

Mid-August

 Fall or early Winter

East View Ranchettes

Mid to Late August

 Fall or early Winter

Rowe Valley Estates

Mid-September

 Fall or early Winter

Gabriel Farms

Mid to Late September             

 Fall or early Winter

Mustang Creek North

Mid to Late September

 Fall or early Winter

Ashley Moore

NA  Spring
Brushy Creek

NA Spring
Candle Oaks

NA Spring
Cat Hollow

NA Spring
Chaparro Estates

NA Spring
Country West

NA Spring
Denchar

NA Spring
Fern Bluff

NA Spring
Fountainwood Estates

NA Spring
Four T Ranch

NA Spring
Giles Estates

NA Spring
Great Oaks

NA Spring
Green Ridge

NA Spring
Hillside at Brushy Creek

NA Spring
Historic Acres

NA Spring
North Lake

NA Spring
North Lakewood

NA Spring
Oak Crest Ranchettes

NA Spring
Oakcreat Estates Highcrest

NA Spring
Ridgewood Estates

NA  Spring
Robles Grandes

NA Spring
Sanaloma Estates

NA Spring
Serenada Country Estates

NA Spring
Serenada East

NA Spring
Serenada West

NA Spring
Shady Oaks Estates

NA Spring
Stone Canyon

NA Spring
Tonkawa Springs

NA Spring
Tonkawa Village

NA Spring
Twin Springs

NA Spring
Wood Ranch 

NA Spring

Updated: 5/30/2017

The Williamson County Road and Bridge Department will notify residents in advance of the work by door hangers, flashing message signs, or static message signs. If your subdivision is receiving door hangers, you can expect to receive a green door hanger approximately 2 weeks in advance of the work and an orange door hanger approximately 2-3 days in advance. If your subdivision is receiving a flashing message board, the message board will be placed approximately a week in advance of the work. After receiving advance notification, please check this page to see if your street is scheduled for the next two days of work.